Holiday Testing of Protective Coatings: What to Agree Before Inspection

Planning coating holiday testing? Agree the method, readiness, inspection coverage, acceptance references and reporting before booking the work.

By Paint Inspection Ltd

A protective coating can look continuous and still contain small gaps that a visual inspection does not reveal. Holiday testing uses electrical equipment to help locate discontinuities in suitable coating systems. The useful question for a project team is not simply whether a detector is available, but whether the proposed test is appropriate and what its results will mean.

For asset owners and contractors arranging inspection, a clear brief helps connect the test to the coating specification, the condition of the work and the evidence needed for acceptance.

What is a holiday in a protective coating?

In this context, a holiday is a discontinuity in the coating, such as a pinhole or an area of missing coating. Electrical detection relies on a suitable circuit between the test electrode and the conductive substrate. It is therefore important to establish the substrate and coating characteristics before choosing the equipment.

Holiday testing answers a particular question about coating continuity. It does not replace a thickness survey, adhesion assessment or investigation of coating condition. A report should make clear which of those questions the inspection actually addressed.

Identify the coating system and the applicable requirements

Provide the coating specification, product information and the required inspection method with the enquiry. State whether the coating is newly applied or has already been in service, and identify the substrate.

The published scope of ISO 29601:2026 covers porosity assessment of protective paint on metallic substrates, limited to electrically non-conductive parts of the paint system. Its scope also highlights the need to consider substances that may have entered coatings during service.

The project documents should identify the applicable method and edition. A newer publication should prompt a document review, rather than an unrecorded change to a contract requirement.

Agree how the test method will be selected

Low-voltage wet-sponge and high-voltage techniques have different operating principles and applications. A wet-sponge detector uses a moistened sponge to help form an electrical path through a discontinuity. High-voltage equipment applies a charged electrode to the coating surface. DeFelsko’s explanation of voltage selection describes why the method and settings need to suit the coating.

There is no single voltage that can be recommended for every asset from a brief description or photograph. Establish the governing procedure, relevant coating thickness information, instrument suitability and manufacturer guidance before agreeing the test arrangements.

Confirm readiness before booking the inspection

The coating needs to be ready for the selected method. ASTM D5162-24 identifies drying or curing and conductive constituents as matters requiring coating-manufacturer input. It also describes limitations when testing coatings that have previously been immersed.

For planning purposes, ask who will confirm readiness and what information the inspector will receive. If the available records do not establish the coating system or its condition, the first assignment may need to be an assessment of suitability for testing.

High-voltage equipment introduces electrical and spark hazards. The equipment instructions and site arrangements need competent review before testing.

Define the areas to be examined

Mark the intended inspection areas on drawings, photographs or an agreed location schedule. Explain whether the brief concerns a complete accessible area, specified components or selected locations. Identify areas that will be covered, enclosed or otherwise unavailable later.

Ask how inaccessible areas and interruptions will be recorded. A result from one accessible area should not be presented as evidence that every part of an asset has been tested. Where access is difficult, discuss the access arrangements alongside the inspection scope. Remote photographs do not perform an electrical continuity test.

Agree the acceptance and repair process

Before testing, identify the document that defines acceptable results and who has authority to accept the work. Finding a discontinuity, recording it and deciding how it will be repaired are separate steps.

Agree how indications will be located and referenced, who will arrange any remedial work, and what inspection is required afterwards. Keep the repair and reinspection records connected to the original finding so that the project team can distinguish outstanding indications from completed actions.

Ask for a report that explains the coverage

A useful reporting brief should request:

  • The asset reference and the areas examined, with coverage limitations.

  • The coating and substrate information used to plan the test.

  • The governing procedure and the equipment and settings recorded for the inspection.

  • Traceable locations for findings and relevant photographs.

  • The acceptance reference, outstanding actions and any subsequent reinspection.

These are practical headings for agreeing deliverables, not a substitute for the records required by the applicable procedure. Review the proposed report alongside the scope before commissioning the work.

Planning holiday testing with Paint Inspection Ltd

Paint Inspection Ltd provides holiday and discontinuity testing as part of its independent coating inspection services. To discuss an assignment, send the asset location, substrate, coating specification, application or service history, intended inspection area and programme.

Tell us about your project so we can discuss the inspection scope and the information needed to assess the proposed testing.

PRACTICAL INSPECTION NOTE

Agree coating system, readiness, coverage, governing procedure, acceptance and reporting before inspection.

RELATED STANDARDS

ISO 29601:2026; ASTM D5162-24. Applicable project edition and controlled procedure govern.

This technical content is provided as general guidance and does not replace the requirements of the applicable project specification, coating manufacturer or current edition of the referenced standard. Official standards should always be obtained from the relevant standards organisation.